Southeast Terminal Expansion Project, Edmonton International Airport
New terminal building, parkade and support facilities (utilities plant, surface parking
areas and roadways). Electrical services include a new consolidated 25 KV distribution
for entire site including 4 unit substations with anticipated demand of 7 MVA.
Emergency distribution is a multiple generator synchronized system representing 2.5
MVA capacity. Design includes state of the art electronic passenger routing, baggage
handling and information display systems, energy efficient lighting, current technology
life safety and security system. HEI provided full electrical engineering services. Completed in 2000.